Construction Update May 22, 2024

posted in: Construction Updates | 0

In this issue:

    • Fountaingrove Road Repairs Underway
    • Coffey Park Paving Locations and Impacts
    • Construction Photos
    • Project Overview
    • Construction Notes

Fountaingrove Road Repairs Underway

[updated!] The initial phase of paving restoration started in Fountaingrove on Monday, May 20, and is expected to last for approximately 2-3 weeks, pending weather delays and other unforeseen circumstances. The work being performed will consist of removing and replacing damaged sections of the road surface. The contractor will return at a later date to apply a slurry seal to the entire road surface.

As of now, there are no full road closures expected while this work is underway. At a minimum, one lane of traffic will remain open at all times. If road closures are needed detour routes will be established to provide access to residents. Traffic control personnel will be on-site to safely direct cars through the work zone when traffic control measures are in place. Drivers should anticipate potential delays and allow for extra time when traveling through the area.

Some homes that have work being performed directly in front of the driveway will have vehicle access restricted to the driveway the day that work is being performed. If you will need your car during the work period in front of your driveway, please park it on an adjacent street before 8 a.m. on the day of the work.

If you have questions regarding the upcoming work please call the project information line at (707) 385-1239.

Please Note:

  • While this work is underway there will be ‘No Parking’ signs posted along the street.
  • Work hours, including ‘No Parking’ hours, are from 8:00 am to 5:00 pm., Monday through Friday.
  • All driveways will have access at the end of each workday.
  • Emergency vehicle access and/or resident evacuation in event of emergency will always be accommodated.
  • If you will need to use your vehicle on your street’s paving days, please park on an adjacent street.
  • There will be some periods of up to several hours where vehicle access will not be possible into or out of homes where road repair work is taking place directly in front of the driveway.
  • If you have special/urgent circumstances requiring getting your vehicle in or out of your driveway while the work is taking place, please make contact with one of the on-site inspectors and they will assist you with access.
  • Trash/recycling collection will be accommodated via coordination with the collection service.
  • Mail and package deliveries should not be impacted by construction activities. When needed, delivery vehicles are parked away from the construction zone and mail/packages are delivered on foot.

When traveling on or near the streets being paved, please use extra caution and watch for construction crews, equipment, flaggers, and special construction/traffic signage.

Coffey Park Paving Locations and Impacts

[updated!] There are no paving operations scheduled in the Coffey Park neighborhood for the next 2-3 weeks.

Paving operations are expected to resume in Coffey Park in the beginning of June. A more detailed schedule and location of work will be provided in subsequent updates.

Construction Photos

Removing a damaged section of the road surface
Removing a damaged section of the road surface

 

Replacing a damaged section of the road surface with new asphalt
Replacing a damaged section of the road surface with new asphalt

 

Project Overview

The project will resurface 33-miles of residential City streets damaged following the 2017 Tubbs Fire. Two pavement treatment options will be applied to resurface the pavement on this project. One pavement treatment option will involve a mill-and-fill asphalt replacement and the other involves dig-out repairs and application of a latex-modified, high-volume traffic slurry seal treatment. The type of treatment applied to a street depends on the pavement condition of the roadway. The project will also include the installation of over 100 ADA-compliant pedestrian curb ramps.

Construction Notes

As with all large construction projects, there will be unavoidable disruptions to nearby neighbors and to motorists traveling in the area – we apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences. When driving, walking, or biking in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadways. Use an alternate route if possible, and allow for additional time to get to and from your destination.


For information about the Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery Project and to ensure you are getting up-to-date project information, visit the Project web page at www.NeighborhoodRoadRecovery.com. Please share this information with your neighbors.

If you have questions or concerns about this project, send an email to info@NeighborhoodRoadRecovery.com or call the project information line at (707) 385-1239.

Thank you for your patience and cooperation!