Construction Update March 27, 2024

posted in: Construction Updates | 0

In this issue:

  • Work Underway and Upcoming
  • Community Meeting
  • Project Photos
  • Project Overview
  • Construction Notes

Work Underway and Upcoming

Note – the schedule is subject to change due to inclement weather and other unforeseen circumstances.

[updated!] Over the next two weeks, construction crews will continue removing existing pedestrian curb ramps and replacing them with new, ADA-compliant, ramps in the following areas around the Coffey Park Neighborhood:

  • Skyview Drive and Crestview Drive
  • Dogwood Drive and Holly Park Way

Starting the week of April 8 the contractor is planning to begin removing existing pedestrian curb ramps in the streets around Dennis Lane and Mocha Lane.

While this work is underway there may be times when ‘No Parking’ signs are posted adjacent to the curb ramps being replaced; however, only a few spots will be affected at a time. Additionally, sidewalks will be closed in the area of work and pedestrians will be redirected to the other side of the street for safety.

When traveling through the area please be on the lookout for construction personnel and follow all construction signage. Noise-generating working hours will be between the hours of 8:00 A.M. to 5:00 P.M., with lane closures allowed between the hours of 8:30 A.M. and 4:00 P.M.

As the project progresses the location of upcoming work and impacts to residents will continue to be provided in subsequent weekly newsletters.

Traffic and driveway access will NOT be impacted while work on the pedestrian curb ramps is underway. Additionally, there are no road closures anticipated for the next several weeks.

Community Meeting

[new!] With paving operations tentatively scheduled to begin in late April, the City is planning to host a community meeting prior to the commencement of pavement activities, where residents can learn more about the project. More information on the time and location of the community will be provided in subsequent newsletters when it becomes available.

Project Photos

[new!] Here are some recent photos of work on the Neighborhood Road Recovery Project

 

Preparing the subgrade for a new pedestrian curb ramp
Preparing the subgrade for a new pedestrian curb ramp

 

Creating the forms before pouring the concrete for a new pedestrian curb ramp
Creating the forms before pouring the concrete for a new pedestrian curb ramp

 

Project Overview

The project will resurface 33-miles of residential City streets damaged following the 2017 Tubbs Fire. Two pavement treatment options will be applied to resurface the pavement on this project. One pavement treatment option will involve a mill-and-fill asphalt replacement and the other involves dig-out repairs and application of a latex-modified, high-volume traffic slurry seal treatment. The type of treatment applied to a street depends on the pavement condition of the roadway. The project will also include the installation of over 100 ADA-compliant pedestrian curb ramps.

Construction Notes

As with all large construction projects, there will be unavoidable disruptions to nearby neighbors and to motorists traveling in the area – we apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences. When driving, walking, or biking in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadways. Use an alternate route if possible, and allow for additional time to get to and from your destination.


For information about the Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery Project and to ensure you are getting up-to-date project information, visit the Project web page at www.NeighborhoodRoadRecovery.com. Please share this information with your neighbors.

If you have questions or concerns about this project, send an email to info@NeighborhoodRoadRecovery.com or call the project information line at (707) 385-1239.

Thank you for your patience and cooperation!