In this issue:
- Project Schedule
- Project Overview
- Construction Notes
Project Schedule
(NOTE – rain anticipated in the weather forecast is likely to impact the work schedule over the next two weeks):
Weather permitting, crews will continue saw-cutting and demolition of the existing pedestrian curb ramps near the intersection of Willowview Court and Skyview Drive. Noise-generating working hours will be between the hours of 8:00 A.M. to 5:00 P.M., with lane closures allowed between the hours of 8:30 A.M. and 4:00 P.M.
Over the next several weeks construction crews will continue removing curb ramps in this area of the Coffey Park neighborhood and replacing them with new, ADA-compliant pedestrian curb ramps. While this work is underway there may be times when ‘No Parking’ signs are posted adjacent to the curb ramps being replaced; however, only a few spots will be affected at a time. Additionally, sidewalks will be closed in the area of work and pedestrians will be redirected to the other side of the street for safety.
As the project progresses the location of upcoming work and impacts to residents will continue to be provided in subsequent weekly newsletters.
Traffic and driveway access will NOT be impacted while work on the pedestrian curb ramps is underway. Additionally, there are no road closures anticipated for the next several weeks.
Project Overview
The project will resurface 33-miles of residential City streets damaged following the 2017 Tubbs Fire. Two pavement treatment options will be applied to resurface the pavement on this project. One pavement treatment option will involve a mill-and-fill asphalt replacement and the other involves dig-out repairs and application of a latex-modified, high-volume traffic slurry seal treatment. The type of treatment applied to a street depends on the pavement condition of the roadway. The project will also include the installation of over 100 ADA-compliant pedestrian curb ramps.
Construction Notes
As with all large construction projects, there will be unavoidable disruptions to nearby neighbors and to motorists traveling in the area – we apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences. When driving, walking, or biking in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadways. Use an alternate route if possible, and allow for additional time to get to and from your destination.
*****************************
For information about the Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery Project and to ensure you are getting up-to-date project information, visit the Project web page at www.NeighborhoodRoadRecovery.com. Please share this information with your neighbors.
If you have questions or concerns about this project, send an email to info@NeighborhoodRoadRecovery.com or call the project information line at (707) 385-1239.
Thank you for your patience and cooperation!