Construction Update August 28, 2024

posted in: Construction Updates | 0

In this issue:

  • Fountaingrove Community Meeting Held August 21
  • Paving Operations in Fountaingrove Scheduled to start September 23
  • No Work on the Labor Day Holiday
  • Fountaingrove Curb/Ramp Replacement Continues
  • Coffey Park Paving Complete
  • Project Overview
  • Construction Notes

Fountaingrove Community Meeting Held August 21

[updated!] Over 75 people attended the online community information meeting on August 21 to learn about the pavement operations for the Neighborhood Road Recovery Project. The meeting focused on the Fountaingrove neighborhood and included information about the project schedule and phases, types of work, what neighbors can expect during the work, and plans for access in the event of fire or other emergency. A PDF of the slide presentation is available here, and a video of the entire meeting is available here.

Fountaingrove Paving Operations Scheduled to Start September 23

[updated!] Paving operations in the Fountaingrove area are anticipated to get underway on September 23, and continue on various streets into early November.

This significant work will generally consist of grinding down specified roadways and then installing a new layer of asphalt. Typical working hours will be 7:00 a.m. to 5:00 p.m., although any lane closures will not begin until 8:00 a.m. Some lane closures may go past 5:00 p.m., depending on the weather and the speed at which the asphalt cools. More information about what to expect during this phase will be provided in upcoming newsletters.

No Work on Labor Day Holiday

Just a reminder – crews will not be working on the Labor Day holiday, Monday September 2.

Fountaingrove Curb/Ramp Replacement Continues

Construction crews are continuing to remove existing pedestrian curb ramps and replace them with new, ADA-compliant ramps, throughout the Fountaingrove neighborhood. This work is expected to continue for the next several weeks.

While this work is underway there may be times when ‘No Parking’ signs are posted adjacent to the curb ramps being replaced; however, only a few spots will be affected at a time. Additionally, sidewalks will be closed in the area of work and pedestrians will be redirected to the other side of the street for safety.

Coffey Park Paving Complete

Paving and striping operations are now complete in the Coffey Park neighborhood. The contractor will continue working on minor punchlist items and clean up over the next few weeks. Weather permitting, the contractor will be back onsite in the Coffey Park neighborhood early next year to apply slurry seal to streets identified to receive that treatment.

Project Overview

The project will resurface 33-miles of residential City streets damaged following the 2017 Tubbs Fire. Two pavement treatment options will be applied to resurface the pavement on this project. One pavement treatment option will involve a mill-and-fill asphalt replacement and the other involves dig-out repairs and application of a latex-modified, high-volume traffic slurry seal treatment. The type of treatment applied to a street depends on the pavement condition of the roadway. The project will also include the installation of approximately 330 ADA-compliant pedestrian curb ramps.

Construction Notes

As with all large construction projects, there will be unavoidable disruptions to nearby neighbors and to motorists traveling in the area – we apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences. When driving, walking, or biking in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadways. Use an alternate route if possible, and allow for additional time to get to and from your destination.


For information about the Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery Project and to ensure you are getting up-to-date project information, visit the Project web page at www.NeighborhoodRoadRecovery.com. Please share this information with your neighbors.

If you have questions or concerns about this project, send an email to info@NeighborhoodRoadRecovery.com or call the project information line at (707) 385-1239.

Thank you for your patience and cooperation!