Construction Update August 14, 2024

posted in: Construction Updates | 0

In this issue:

  • Coffey Park Paving Complete
  • Fountaingrove Community Meeting
  • Fountaingrove Pedestrian Curb Ramps
  • Construction Photos
  • Project Overview
  • Construction Notes

Coffey Park Paving Complete

[updated!] Paving operations are now complete in the Coffey Park neighborhood. The contractor has begun laying down the permanent striping on the newly paved road surfaces. This work is expected to last 2-3 days and cause minimal impacts to the public.

 Weather permitting, the contractor will be back onsite in the Coffey Park neighborhood early next year to apply a slurry seal to streets requiring that treatment.

Fountaingrove Community Meeting

[update!] The City is hosting an online community meeting on Wednesday, August 21 at 5:30 p.m. to discuss pavement operations which is scheduled to resume in the beginning of September in the Fountaingrove Neighborhood. The meeting will cover the project schedule and phases, types of work, what neighbors can expect during the work, and plans for access in the event of fire or other emergency.

The following methods are available to access the meeting:

August 21, 2024 at 5:30 p.m.

  • Online: click here to join
  • or Call in: 888-475-4499 (US toll free)
  • Meeting ID: 839 9465 6308

There will be a question-and-answer period during the meeting. To submit questions in advance email them to info@neighborhoodroadrecovery.com. For more information about the meeting visit the project website at www.neighborhoodroadrecovery.com

Fountaingrove Pedestrian Curb Ramps

[new!] Construction crews are continuing to remove existing pedestrian curb ramps and replace them with new, ADA-compliant ramps, throughout the Fountaingrove neighborhood. This work is expected to continue for the next several weeks.

While this work is underway there may be times when ‘No Parking’ signs are posted adjacent to the curb ramps being replaced; however, only a few spots will be affected at a time. Additionally, sidewalks will be closed in the area of work and pedestrians will be redirected to the other side of the street for safety.

Construction Photos

[updated!]
Laying the permanent striping line for a stop sign
Laying the permanent striping line for a stop sign

 

Placing the permanent striping along one of the newly paved roads
Placing the permanent striping along one of the newly paved roads

 

Project Overview

The project will resurface 33-miles of residential City streets damaged following the 2017 Tubbs Fire. Two pavement treatment options will be applied to resurface the pavement on this project. One pavement treatment option will involve a mill-and-fill asphalt replacement and the other involves dig-out repairs and application of a latex-modified, high-volume traffic slurry seal treatment. The type of treatment applied to a street depends on the pavement condition of the roadway. The project will also include the installation of approximately 330 ADA-compliant pedestrian curb ramps.

Construction Notes

As with all large construction projects, there will be unavoidable disruptions to nearby neighbors and to motorists traveling in the area – we apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences. When driving, walking, or biking in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadways. Use an alternate route if possible, and allow for additional time to get to and from your destination.


For information about the Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery Project and to ensure you are getting up-to-date project information, visit the Project web page at www.NeighborhoodRoadRecovery.com. Please share this information with your neighbors.

If you have questions or concerns about this project, send an email to info@NeighborhoodRoadRecovery.com or call the project information line at (707) 385-1239.

Thank you for your patience and cooperation!