Construction Update July 31, 2024

posted in: Construction Updates | 0

In this issue:

  • Coffey Park Paving Locations and Impacts
  • Community Meeting
  • Construction Photos
  • Project Overview
  • Construction Notes

Coffey Park Paving Locations and Impacts

[updated!] Paving operations are nearly complete in the Coffey Park neighborhood.

The contractor is currently working on Hopper Avenue and is expected to complete paving by Thursday, August 1.

Once paving is complete the contractor will begin installing striping along the newly paved roads in the Coffey Park neighborhood. Road striping is anticipated to last for approximately two weeks, with minimal disruptions to residents and motorists.

For more information on the project please visit the website at www.NeighborhoodRoadRecovery.com.

Please Note:

  • There may be times when the contractor needs to trim tree branches hanging over the road so that the paving equipment can safely pass without breaking the branches.
  • While this work is underway there will be ‘No Parking’ signs posted along the street.
  • Work hours, including ‘No Parking’ hours, are from 8:00 am to 5:00 pm., Monday through Friday.
  • All driveways will have access at the end of each workday.
  • Emergency vehicle access and/or resident evacuation in event of emergency will always be accommodated.
  • If you need to use your vehicle on your street’s paving days, please park on an adjacent street.
  • If you have special/urgent circumstances requiring getting your vehicle in or out of your driveway while the work is taking place, please make contact with one of the on-site inspectors or call (707) 385-1239 for assistance.
  • Trash/recycling will be collected on the normally scheduled day before construction hours. If Recology is unable to collect the trash on that day they will make every effort to collect the trash bins on the following day.
  • Mail and package deliveries should not be impacted by construction activities. When needed, delivery vehicles are parked away from the construction zone and mail/packages are delivered on foot.

When traveling on or near the streets being paved, please use extra caution and watch for construction crews, equipment, flaggers, and special construction/traffic signage.

Community Meeting

[new!] The City is hosting an online community meeting on Wednesday, August 21 at 5:30 p.m. to discuss pavement operations which is scheduled to start the beginning September in the Fountaingrove Neighborhood. The meeting will cover the project schedule and phases, types of work, what neighbors can expect during the work, and plans for access in the event of fire or other emergency.

More information regarding the meeting will be provided in subsequent newsletters.

Construction Photos

[updated!]
Compacting the newly poured asphalt
Compacting the newly poured asphalt

 

Installing and compacting the new asphalt
Installing and compacting the new asphalt

 

Project Overview

The project will resurface 33-miles of residential City streets damaged following the 2017 Tubbs Fire. Two pavement treatment options will be applied to resurface the pavement on this project. One pavement treatment option will involve a mill-and-fill asphalt replacement and the other involves dig-out repairs and application of a latex-modified, high-volume traffic slurry seal treatment. The type of treatment applied to a street depends on the pavement condition of the roadway. The project will also include the installation of approximately 330 ADA-compliant pedestrian curb ramps.

Construction Notes

As with all large construction projects, there will be unavoidable disruptions to nearby neighbors and to motorists traveling in the area – we apologize in advance for noise, dust, lane closures, traffic delays, and any other impacts or inconveniences. When driving, walking, or biking in the area, always be aware of construction crews and equipment, flaggers, special signage, slower traffic, and rough roadways. Use an alternate route if possible, and allow for additional time to get to and from your destination.


For information about the Coffey Park and Fountaingrove Neighborhood Road Disaster Recovery Project and to ensure you are getting up-to-date project information, visit the Project web page at www.NeighborhoodRoadRecovery.com. Please share this information with your neighbors.

If you have questions or concerns about this project, send an email to info@NeighborhoodRoadRecovery.com or call the project information line at (707) 385-1239.